EDF
CONFIRMS EARLY DISMANTLING OF
FIRST-GENERATION REACTORS
Electricite
de France (EDF) has decided to take a faster track
on decommissioning its first-generation nuclear power units, the utility
confirmed late last month.
A spokesman
said top management had signed off on a 20-billion-franc
(about U.S.$2.9-billion) program to dismantle its eight oldest reactors,
all shut permanently, by 2020-2025,
about 25 years earlier than EDF originally planned.
Pierre Rolland,
head of the decommissioning program in
EDF’s engineering division, said the utility wants to “demonstrate
concretely its capacity to carry out complete deconstruction,” using
the term coined at EDF a few years ago
to cover the entire decommissioning process. The utility has been
under pressure from safety authority DSIN to
speed dismantling programs, in part because of what DSIN
chief Andre-Claude Lacoste considers the risk of losing
information about a shuttered plant over longer periods.
However, EDF
officials said, the utility’s policy toward dismantling
its standardized large PWRs hasn’t changed. Up
to now, EDF has said it will wait 50 years before total deconstruction
of the PWRs, but is considering, with encouragement from DSIN, whether a 25-year timeline might be
more advantageous.
The eight
first-generation units are: the 70-MW heavy water reactor at Brennilis, half-owned by the
Commissariat a l’Energie Atomique; the Chooz-A prototype PWR, half-owned
by Electrabel;
and six gas-cooled, graphite-moderated units
at Chinon, St. Laurent-des-Eaux, and Bugey. The
decision, which still must be confirmed by EDF’s board
of directors, also concerns the Creys-Malville fast breeder
plant, shut prematurely in 1998.
Policy Decisions
EDF expects
to present the new policy to DSIN shortly, once
the decision is endorsed by the board.
EDF’s
resolve to dismantle the gas-cooled reactor plants
within 25 years contrasts with the policy adopted up to
now by British Nuclear Fuels plc and British Energy, which
have said they want to wait 70 to 100 years or more after
reactor closure to take their magnox and AGR sites to greenfield
status. A prominent U.K. consultant, Gordon MacKerron,
said that policy puts the U.K. “in an uncomfortable position” given that other OECD countries’utilities
expect to
have discharged their decommissioning liabilities by 2060 at the latest
(NW, 2 Nov. ’00, 10).
Fuel has been
removed from all the sites except for Creys-Malville, where it is
under way but has been delayed by special problems. Removal of fuel
and operational waste corresponds
to Level 1 dismantling as defined by the IAEA. Rolland said that EDF’s policy
aims to reach Level 2 status for
the nine closed units within five to 10 years. Level 2 consists
in reducing the controlled (radioactive) zone of the installation
to the reactor building and removing all parts that can be dismantled easily. Each new dismantling stage
requires
a new license under French regulations.
Expensive Jobs
In an interview,
Rolland said EDF’s studies project that dismantling
of the utility’s GCRs will be “considerably more
expensive” than the same job for its 58 standardized PWR
units. Studies concluded at the end of 1999 confirmed earlier estimates
that decommissioning the PWRs will
cost about 15% of their complete construction cost, or around FF 1.5-billion
for a 900-MW PWR unit. Deconstructing the 70-MW HWR at Brennilis,
on the other hand, is
expected to cost a total of FF 2-billion, of which half falls to EDF. Brennilis represents something of an extreme,
he said,
because of its 200 fuel channels, its size (about the same as a 900-MW
PWR) and relative complexity, and the lack
of the “series factor” that applies to the LWRs.
The gas-cooled
reactors, whose nominal capacities range between 200 megawatts and
540 megawatts, are projected
to cost FF 1.8-billion (in today’s money) on average
to dismantle to Level 3, Rolland said. The 300-MW
Chooz-A PWR will cost more than other PWRs, or about
FF 1.7-billion, because of the reactor’s unique loca-tion inside a cavern.
The 1,200-MW
Superphenix breeder plant at Creys-Malville is
another case entirely, not only because fuel removal
is complicated but also because some 5,000 tons of sodium coolant
must be removed and decontaminated. Rolland
said deconstruction of Creys-Malville components won’t begin until the second half of this decade.
The original Creys-Malville partners—EDF and a group of foreign utilities
that have now withdrawn—considered a “realistic” estimate
of the dismantling cost to be FF 5.8-billion, not including disposition of its plutonium fuel. That
worked out
to 18% of the original construction cost. Rolland said late last month
that EDF, the sole owner now, expects to spend a total of more than
FF 20-billion over 20 years or so to
totally dismantle the plant and deal with the fuel and sodium.
A final decision on the fate of the Creys-Malville sodium
is expected this year. EDF has provisionally planned
to treat it between 2005 and 2012-2013.
EDF's deconstruction
provisions, which are kept as special line item on the utility’s books,
totalled about FF 50-billion
at the end of last year. Rolland said EDF adds about FF 4-billion
each year to the fund based on “periodic adjustments”
of projected requirements.
The Brennilis
dismantling program, which was supposed to be a model program, has run into numerous delays, associated
partly with the dual management by EDF and
the CEA. Last year, the CEA asked for, and obtained, transfer
of the operating license for the shut facility to EDF, after the project
had accumulated some four years’ delay.
Level 2 dismantling was scheduled
to be completed at the end
of last year and Level 3 studies have begun, but imple-mentation is
slower than anticipated.
Besides organization,
EDF’s biggest problem in dismantling the
first-generation units is the lack of waste disposal
sites. Rolland observes that the French utility “isn’t so bad off”
because it has a low-level waste disposal site at Soulaines. But national radwaste management company
Andra has
experienced delays in licensing a planned site
for disposal of very low-level waste (VLLW) which it hopes
to build alongside the existing low- and medium-level waste
(LLW/MLW) center at Soulaines, and last autumn told DSIN the site
might not be ready until mid-2004 (NW, 5 Oct. ’00, 13).
Recently,
DSIN issued an order to EDF requiring it to have storage sites ready
to accept VLLW “no later than four years
from now.”
Another thorny
problem for the GCRs is their graphite moderator blocks and fuel channel
sleeves, which do not qualify for disposal at Soulaines because of
their alpha content.
Rolland said having a disposal facility for the 17,000
metric tons of graphite at the six units is a priority for EDF. Andra
has developed a conceptual design for a disposal
facility for low-level alpha-bearing wastes in a clay
formation, but there’s no site identified yet. Rolland said EDF is basing its program on the availability of a
graphite disposal center in 2010.
Dedicated
disposal sites for long-lived MLW and for high-level waste aren’t
expected to be available until 2020, but
the volumes of those wastes are much lower than for the lower-activity
categories.
The lack of waste sites is
already posing a big problem
for EDF at
Brennilis. The original 1996 decommissioning license
for the HWR facility allowed two years’ interim storage
of waste on site; EDF asked for a two-year extension, and received authorization for one additional
year. Last year, EDF asked for 1.5
years more and received another year’s
extension. An EDF official said last autumn that the utility
was “expecting” DSIN to react and was girding for new
licensing procedures.
A review of
EDF’s decommissioning waste projections, presented
by Michel Campani of the utility’s Nuclear Operations division to the Safewaste 2000 conference in Montpellier
last year, estimated the following volumes of waste from
decommissioning the eight first generation units:
—Metallic
waste: 25,000 MT of VLLW, an equivalent mass
of short-lived LLW/MLW, and 200 MT of long-lived MLW;
—Graphite: 15,000 MT of long-lived LLW;
—Concrete:
70,000 MT of VLLW and 75,000 MT of short-lived
LLW/MLW;
—Miscellaneous:
1,800 MT of VLLW and 1,400 MT of short-lived
LLW/MLW.
In contrast,
decommissioning of a typical four-unit PWR site is expected
to produce 17,000 MT of VLLW, 9,500 MT of short-lived LLW/MLW,
and 500 MT of long-lived MLW in the metallic category;
900 MT of insulation (VLLW); and a total of 1,900 MT of
concrete, about half of it VLLW.