WANA
NEWS - NEWYDDION CWNC
|
August
|
2003
|
Awst
|
CONTENTS
|
Puzzle over plant's future Sellafield's Thorp reprocessing operation,
once hailed as the saviour of the British nuclear industry with
its promise of producing limitless electricity throughout the 21st
century, may close by 2010. Although BNFL later played this report
down, it is known that: This is because the dangerous liquid waste produced by reprocessing cannot be disposed of fast enough to satisfy the government's safety regulators. A Nuclear Installations Inspectorate report, published in June stated: "The site vitrification performance ... means that Oxide fuel reprocessing will continue to be significantly constrained for the foreseeable future by vitrification throughput." It was announced in July that Thorp may take an extra three years to complete its existing reprocessing contracts. In its best year, 1999-2000, Thorp's throughput was 890 tonnes. However, this fell to 362 tonnes the following year and was just 502 tonnes last year. In March at the end of its ninth year it still had 2,626 tonnes to go. This year BNFL has set a target output of 671 tonnes, though Thorp has rarely met its output targets. Even if it is successful, there will still be 1,955 tonnes of waste left to reprocess at the end of March, around three years' work. Thorp was designed with a nominal capacity of 12,000 tonnes over a ten year period. BNFL decided that the plant would only be called upon to reprocess 6,000 tonnes in the first decade. (Harold Bolter, 'Inside Sellafield' - 1996. P75) In the late 1980's 'in order to placate its overseas customers' BNFL announced that it would be treated as a plant with a working capacity of 7,000 tonnes over the first ten years. When BNFL built Thorp, it predicted it would make a £500m profit on its reprocessing deals, but this has been eaten up by the extra vitrification line and increased running costs at Thorp. Now BNFL is facing large losses as it renegotiates the deals it has with its customers. The Germans, in particular, are understood to be keen to negotiate a discount on their £1.2bn contract with BNFL, which covers the reprocessing of spent fuel from its reactors and the purchase of Mixed Oxide Fuel from the £470m MOX plant built next to Thorp at Sellafield. Vitrification - the truth Watson has now conceded that the vitrification plants continuously
broke down, mainly because the high levels of radiation destroyed
the electrical cables and other machinery needed to operate them.
The plant was designed with two production lines to produce 600
glass blocks a year - enough to make safe 50 years of highly dangerous
liquid waste. These tanks contain the highest level of radioactivity
of any plant in Europe. Magnox fuel has to be reprocessed through the dilapidated B205 plant built in 1965. To cope with the remaining throughput from the magnox stations, it will stay open until 2012. The only manufacturing left on the site when reprocessing goes will be the plant for making nuclear fuel from plutonium and uranium oxides. The MOX plant, opened only last year, takes plutonium from the Thorp plant, but Mr Watson says it can remain open using some of the 75 tonnes of plutonium stored on site. "Ideally, I would like to build a plutonium-burning reactor and use the MOX plant to make the fuel. The rest of the site could then be devoted to cleaning up the mess of the cold war. But these are political decisions," he said. WANA Comment: The NDA may consider stopping reprocessing at THORP even earlier than 2010 because of uncertainties about these orders. The rationale for reprocessing had already vanished before the plant started up in 1994. Even 'insiders' regarded Thorp as 'spherically daft' (daft from whichever way you look at it.) WANA has never campaigned for the closure of the Sellafield site. It hosts a huge concentration of radioactivity and the legacy of fifty years of contamination. With the setting up of the Nuclear Decommissioning Authority, there is a real opportunity to clean up this mess. It is the stated objective of the UK strategy for radioactive discharges 2001-2020 to implement the UK's obligations in respect of the OSPAR strategy rigorously and transparently. Discharges must now be brought down in line with this objective rather than the significant increases currently projected until 2011. Wylfa in trouble again As BNFL prepare the 'safety case' to operate Wylfa beyond 2004, further weld defects have been discovered during the reactor 1 outage, which started on May 9th. These are different defects from those picked up in April 2000 in the superheater penetration welds, but are in the same region of the reactor at the top of the steam generators. Unlike the superheater pipes which were braced from the outside of the reactors, the new defects are in brackets which support steam pipes inside the reactors and require considerably more difficult and arduous welding to be carried out. This latest type of defect was apparently not anticipated before May 9th despite the fact that a huge increase in staff has occurred during the planned outage of Wylfa R1. Almost 1000 people are on site undertaking the outage and shutdown work. (Wylfa News, 12/5/03) In addition to carrying out maintenance work identified during the last few years, they will inspect and collect samples in order to conduct the periodic safety review (PSR). The NII has confirmed that any increase in radiation exposure of station staff has to be justified in terms of the net benefit of longer term plant operations. Wylfa is fast running out of time. The NII expect the PSR documentation from BNFL this September. They then have a year in which to assess it, and decide whether the case for continued operation has been made or not. There goes the environment Ecological monitoring on the effect of the warming of the high
Rhône at the level of the Bugey nuclear power station gives
clear evidence of the impact of the warming on aquatic life: up
to 15°C, the fish progressively leave the margins, up to 25°C
the larger river creatures desert the zone and up to 29°C the
collapse of whole populations occurs. After four years of allowing
exception after exception to help out EdF (the current norms are
themselves already exceptions) the French Environment Ministry has
given consent for discharges up to 29°C. There goes the grid AlQuaeda is even rumoured to be behind the North American blackouts.The growing dependence on larger and larger generating units over the last four or five decades has made US and UK electricity distribution system more vulnerable to breakdowns. The UK Government's Energy White Paper claims (para 6.4) that our energy system has proved robust, yet this is in the context of 'weather related economic losses to communities and businesses (that) have increased ten-fold over the last 40 years'. (para 1.7)A truly robust energy system would employ 'micro CHP' with gas-fired domestic and commercial boilers generating their own electricity. As central heating boilers are replaced on average every 15 years, and the contribution that they could make to electricity supply is over 40 GW, it was curious how the Energy White Paper played them down. The true benefits of electricity supplied by renewable sources are not confined to their non-carbon emitting characteristics but stem from their small size, their geographical spread, and their modular nature. These sources will, in the long term, prove more resilient as well as being more affordable, less complex and having shorter lead times. Trawsfynydd Decision Flunked by Assembly At last November's Trawsfynydd public inquiry WANA had quoted Michael
Barnes, the Hinkley Point C Inspector who remarked: BNFL stated that: The planning application can be determined without consideration of wider issues relevant to decommissioning nuclear power stations because it should be assumed that other regulatory regimes will operate satisfactorily. (para 28) The HSE/NII similarly stated that: Planning Authorities should operate on the basis that the pollutant control regimes will be enforced. They should not concern themselves with the timing of reactor dismantling, or with the merits or demerits of Government policy. It is accepted that there are large areas of policy to be settled, but there are separate processes of deliberation to decide these. (para 84) The Inspector duly obliged, recommending that consent be given. The Assembly's 'planning decision committee' could have asserted an overarching commitment to its sustainable development principles, split the decision and rejected the 'height reduction' part of the application. But it didn't. It was unwise for the National Assembly's Planning Decision Committee to give the go ahead for a £70 million facelift for 40 year old reactor buildings which on safety grounds should be dismantled within 20 years. It would be disastrous if this public money is spent on such a silly project when there is a serious and demanding task ahead. According to the HSE/NII 'the creation of the liabilities management authority resolves concerns about future resources for the decommissioning of nuclear sites.' (para 87) The Nuclear Installation Inspectorate has confirmed that there
is little benefit in delaying the decommissioning of the Trawsfynydd
reactors beyond 30 years after their 1991 shutdown. The reduced height reactor buildings are capable of being made passively safe. (paras 85-86) Comments and Extracts from the Inspector's report and the Assessor's
report The ILW store is a temporary building which should not be permitted to remain longer than it is needed and should, when dismantled be followed by full site restoration. Similar conditions cannot be placed on the "permanent" reactor buildings. (C27-C29) By overturning the inspectors recommendation on a time limit for the ILW store the National Assembly Planning Decision Committee (para 10 of decision letter) may have established by default a permanent radioactive waste dump at Trawsfynydd. The assessor's report The NII's QQR process has influenced the thinking of the licensees
on the timing of Stage 3 decommissioning. 'However there has been
no formal opportunity within the QQR process for other stakeholders
to express a view, either to the licensee or to the NII'. To help
clarify matters at future public inquiries a period of public comment
on the licensee's submissions and/or a period of public consultation
on an initial draft report by the NII, is suggested. "It is
important for decision makers and the public to understand why strategy
in other countries should favour significantly earlier decommissioning
than in the UK." (AR 49ii) The assumption of a 2.5% real growth rate for funds...... "places
a burden on future generations to ensure that funds invested today
grow at a sufficient rate. Furthermore, the lack of a segregated
fund for decommissioning Magnox reactors, as at present, means that
in practice, most of the required funding will likely be borne by
taxpayers in the future." It is questionable whether these
circumstances "satisfy the principles of intergenerational
equity and sustainable development." (AR 49iv) "Construction and operational difficulties could lead to the reduced height safestores being more difficult to manage during the Care and Maintenance phase than if the roof height was not reduced." (AR 63ii) "Although national radioactive waste management policy is currently in a state of turmoil, this decision is unlikely to undermine or run counter to national policy..." (AR68) "Further work is needed to define what is meant by passive safety for any extended Care and Maintenance phase..." (AR 71iii) Amen CORWM Chair lands, by parachute Katharine Bryan has been Chair of the Joint Nature Conservation Committee, the Government's wildlife advisory body, since October 2002. Before that she was Chief Executive of the North of Scotland Water Authority. She previously held senior posts in the Environment Agency and its predecessors. Yes to Wind Published by WANA PO Box 1 Llandrindod Wells LD1 5AA
Hugh Richards Tel/Fax: 01982 570362 |